Phase one is the service the building already has. The upgrade path sits beside it, with the lead time attached. Every step of the arithmetic is on screen.
lights, HVAC, wash bay, tools, IT
What this parcel supports on the service it already has, and what the upgrade path adds.
What this site supportsDerived
| Phase | Service | Vehicles | Time to operating |
|---|---|---|---|
| Today | 800 A existing | 156 | Weeks |
| Upgrade | 1,200 A | 249 | 18 to 36 months, transformer procurement |
| Upgrade | 1,600 A | 343 | 18 to 36 months, transformer procurement |
Start on the service that exists. Upgrade once the site is earning.
Zoning and energy radius require review. They are not screened by this tool.
See the arithmetic
The number above is yours with no email. The full arithmetic chain, land check and a one-page report open with an email address.
This is a screening estimate, not engineering advice. Service capacity, load calculations and code compliance for any specific site must be confirmed by a licensed electrical engineer and the serving utility before commitments are made.